Opening in October and Now Taking Reservations

for November 15th 2020 and Beyond

August 26, 2019

March 9, 2020 – Ground Breaking

March 16, 2020

March 29, 2020

March 30, 2020

March 31, 2020

April 08, 2020

April 09, 2020

April 13, 2020

April 30, 2020

May 6, 2020

May 7, 2020

May 8, 2020

Custom building 5 Porch Swings

May 8, 2020

Installing individual electric conduit to each site

May 28, 2020

Forming up the Maintenance Building.

May 28, 2020

Laying sewer pipe.

June 1, 2020

Three excavators working on underground utilities at the same time.

June 1, 2020

Plumbing the Office, laundry, bathroom building.

June 2, 2020

Plumbing the Office, Laundry, Bathroom Building.

June 2, 2020

Plumbing the Maintenance Building.

June 8, 2020

Office ready to pour concrete.

June 9, 2020

Pouring both Office Building and gutters.

June 10, 2020

Maintenance Building.

June 27, 2020

Pavilion.

July 2, 2020

Framing the 20′ x 70′ site pads with utility pad on the side.

July 2, 2020

Unloading Bollards

July 6, 2020

Unloading Steel for Buildings

July 6, 2020

Hanging Steel

July 6, 2020

Concrete Utility Bib

July 9, 2020

Pouring 20′ x 70′ concrete pads

July 7-9, 2020

Hanging more steel

July 7-9, 2020

Hanging steel Maintenance Building

July 16, 2020

Maintenance Building

July 16, 2020

Pavilion

July 24, 2020

Each pad must be formed, then the electrician brings his conduit for electric and fiber optic to the pedestal on it’s own concrete utility pad then the plumber brings the water and sewer to the utility pad then the electrician checks the work and finally the tractor driver makes certain the red clay is packed and in place prior to the concrete pumper truck delivering the concrete for the 20′ X 70′ pad.

July 24, 2020

Concrete Pumper truck required to move concrete to the back of 70′ long pads

July 30, 2020

Bricking the office

 July 30, 2020

Celebrating the Progress

Aug. 18, 2020

All pictures of the office

Aug. 20, 2020

Laundry room and Men’s bathroom

Aug. 20, 2020

Pouring concrete 20′ by 70′ site pads

Aug. 26, 2020

Framing of the Office and Hand pouring concrete gutters.

Aug. 27, 2020

Framing of the Office and Laying brick on the Pavilion.

Aug. 27, 2020

Framing of the Office and Laying brick on the Pavilion.

Aug. 28, 2020

Framing of the Office and Bathrooms inside the office.

Aug. 29, 2020

Framing of the Office, Laying brick in the Pavilion and Landscaping

Sept. 9, 2020

Brick Pavilion

Sept. 9, 2020

Wiring the Office and Maintenance Building

Sept. 11, 2020

Finishing Site pads

Homestead RV Community is dedicated to providing superior value through friendly service and quality amenities for a reasonable price while creating lasting relationships and fun.

Homestead RV Community
10550 Pioneer Road
Theodore, AL 36582

Looking for an RV Park, RV Camping or RV Campground in the Mobile and Dauphin Island area? Check availability here.

Phone
(251) 973-2484
Email
info@homervc.com

Download our app to access all the information you need to enjoy your stay.